Standard Gauge Railway Phase 2
Multiple, Nairobi, Kiambu, Nakuru
Infrastructure
In Progress
Extension of the Standard Gauge Railway from Nairobi to Naivasha, connecting Kenya's capital to the country's geothermal hub and continuing the flagship railway project towards Uganda.
Project Overview
Timeline
StartedDec 1, 2018
Expected CompletionDec 31, 2024
Budget
AllocatedKES 150,000,000,000
SpentKES 142,000,000,000
Efficiency89%
Impact
Beneficiaries2,500,000 people
Jobs Created8,000 jobs
Economic ImpactKES 4,500,000,000
SDG Goals
SDG 9
SDG 11
SDG 8
Responsible Parties
Implementing Agency
Kenya Railways Corporation
Contractors
- China Road and Bridge Corporation
Key Officials
E
Eng. Philip Mainga
Managing Director, Kenya Railways Corporation
Project Progress
Current status and completion percentage
Overall Completion
78%Timeline
110%
Of timeline elapsed
Budget
95%
Of budget utilized
Milestones
1/1
Milestones completed
Project Milestones
Key milestones and their status
Nairobi-Ngong Section
Completion of Nairobi to Ngong railway section
Completed
Planned: Jun 30, 2022
Actual: Sep 20, 2022