Standard Gauge Railway Phase 2

Multiple, Nairobi, Kiambu, Nakuru
Infrastructure
In Progress

Extension of the Standard Gauge Railway from Nairobi to Naivasha, connecting Kenya's capital to the country's geothermal hub and continuing the flagship railway project towards Uganda.

Project Overview

Timeline

StartedDec 1, 2018
Expected CompletionDec 31, 2024

Budget

AllocatedKES 150,000,000,000
SpentKES 142,000,000,000
Efficiency89%

Impact

Beneficiaries2,500,000 people
Jobs Created8,000 jobs
Economic ImpactKES 4,500,000,000

SDG Goals

SDG 9
SDG 11
SDG 8
Responsible Parties

Implementing Agency

Kenya Railways Corporation

Contractors

  • China Road and Bridge Corporation

Key Officials

E

Eng. Philip Mainga

Managing Director, Kenya Railways Corporation

Project Progress
Current status and completion percentage

Overall Completion

78%

Timeline

110%

Of timeline elapsed

Budget

95%

Of budget utilized

Milestones

1/1

Milestones completed

Project Milestones
Key milestones and their status

Nairobi-Ngong Section

Completion of Nairobi to Ngong railway section

Completed
Planned: Jun 30, 2022
Actual: Sep 20, 2022