Lamu Port Development Project
Lamu, Lamu East
Infrastructure
In Progress
Development of a 32-berth deep water port in Lamu as the anchor project of the LAPSSET Corridor, designed to serve Kenya, South Sudan, and Ethiopia with modern port facilities.
Project Overview
Timeline
StartedJun 20, 2014
Expected CompletionDec 31, 2025
Budget
AllocatedKES 200,000,000,000
SpentKES 125,000,000,000
Efficiency72%
Impact
Beneficiaries5,000,000 people
Jobs Created12,000 jobs
Economic ImpactKES 8,500,000,000
SDG Goals
SDG 9
SDG 8
SDG 17
Responsible Parties
Implementing Agency
LAPSSET Corridor Development Authority
Contractors
- China Communications Construction Corporation
Key Officials
S
Silvester Kasuku
Director General, LCDA
Project Progress
Current status and completion percentage
Overall Completion
65%Timeline
97%
Of timeline elapsed
Budget
63%
Of budget utilized
Milestones
1/1
Milestones completed
Project Milestones
Key milestones and their status
First Berth Completion
Completion and operationalization of the first berth
Completed
Planned: May 20, 2019
Actual: May 20, 2019