Menengai Geothermal Project
Nakuru, Nakuru Town East
Energy
In Progress
Development of a 105MW modular geothermal power complex near Nakuru, featuring three 35MW plants designed to provide clean energy to half a million households through innovative steam-gathering technology.
Project Overview
Timeline
StartedFeb 1, 2019
Expected CompletionDec 31, 2025
Budget
AllocatedKES 25,000,000,000
SpentKES 18,500,000,000
Efficiency85%
Impact
Beneficiaries500,000 people
Jobs Created1,800 jobs
Economic ImpactKES 3,200,000,000
SDG Goals
SDG 7
SDG 13
SDG 8
Responsible Parties
Implementing Agency
Geothermal Development Company
Contractors
- Sosian Energy
- Globeleq
- Kaishan Group
Key Officials
S
Stephen Onyango
Engineer, Geothermal Development Company
Project Progress
Current status and completion percentage
Overall Completion
70%Timeline
94%
Of timeline elapsed
Budget
74%
Of budget utilized
Milestones
1/1
Milestones completed
Project Milestones
Key milestones and their status
Sosian Plant Operational
First 35MW modular plant commissioned
Completed
Planned: Jun 30, 2023
Actual: Aug 15, 2023