Menengai Geothermal Project

Nakuru, Nakuru Town East
Energy
In Progress

Development of a 105MW modular geothermal power complex near Nakuru, featuring three 35MW plants designed to provide clean energy to half a million households through innovative steam-gathering technology.

Project Overview

Timeline

StartedFeb 1, 2019
Expected CompletionDec 31, 2025

Budget

AllocatedKES 25,000,000,000
SpentKES 18,500,000,000
Efficiency85%

Impact

Beneficiaries500,000 people
Jobs Created1,800 jobs
Economic ImpactKES 3,200,000,000

SDG Goals

SDG 7
SDG 13
SDG 8
Responsible Parties

Implementing Agency

Geothermal Development Company

Contractors

  • Sosian Energy
  • Globeleq
  • Kaishan Group

Key Officials

S

Stephen Onyango

Engineer, Geothermal Development Company

Project Progress
Current status and completion percentage

Overall Completion

70%

Timeline

94%

Of timeline elapsed

Budget

74%

Of budget utilized

Milestones

1/1

Milestones completed

Project Milestones
Key milestones and their status

Sosian Plant Operational

First 35MW modular plant commissioned

Completed
Planned: Jun 30, 2023
Actual: Aug 15, 2023